Handicapped equipped bus
2013
CAPITAL PROJECTS COMPLETED
MORSE STREET CARPET MORSE STREET CARPET POWNAL MAIN HALL CARPET Morse street gym and D wing roofs
1
Morse street gym and D wing roofs Middle School Gym Roof Middle School Gym Roof Pownal Trim POWNAL TRIM Mast Landing Playground
2
Mast Landing Playground Maintenance Truck Parking Lot Sander Middle School Choices
Wall Repair Pownal Grade 5 Paper Middle School Life Skills Closet
3
Wall repair Pownal Grade 5 Paper Wall Repair Pownal Grade 5 Paper
Closet Closet
Central Office Basement Central Office Basement
Central Office Wall Repair Central Office Wall Repair4
CENTRAL OFFICE NATURAL CENTRAL OFFICE NATURAL
GAS CONVERSION GAS CONVERSION
1485 Gallons of heating oil Cost to convert to natural Gas $3,850
First year savings $2,914
1485 Gallons oil @ $3.70 = $5,494 Rebate $1,000
2064 Therms of Natural Gas= $2,580
Year one rebate for conversion $1,000 Payback for conversion in first winterTotal Cost Avoidance Since 2014-2015
Anticipated Capital Budget Natural Gas 2010-2013 Taken from RSU5 Capital Plan
$464,514 Adopted January 2010
Revised 10-09-2013
2014-2015 Anticipated Capital Budget
2014-2015 Anticipated Capital Budget
(Failed Referendum)
Bus (2) 78 Passenger (funded through retired debt) $0
Bus (2) 77 Passenger (funded through retired debt) $0 High School Roof Replacement 100,200 & 300 wings $250,000
Middle School repave access road $150,000
Field Maintenance Tractor $33,000 Field Maintenance Tractor $33,000
Morse Street Steamer $15,000 Pownal Playground upgrade $10,000
Middle School Carpet Library $12,000 Morse St Steamer (kitchen) $15,000
Pownal Gym Roof $30,000
Dish Washer Mast Landing $14,000 Middle School Carpet Library $12,000
Middle School Reach in cooler $9,000 Dish washer Mast Landing $14,000
High School add cabinets to room 401 $15,000 Middle School reach in cooler $9,000
Audio Video Upgrade $55,000
Capital Reserves $67,000 High School add cabinets to room 401 $15,000
Total $400,000 Capital Reserves $42,000Total $400,000
5
Two 77 passenger buses Middle repave access road
Field Maintenance Tractor Morse Street Steamer Middle School Library Carpet Pownal Gym Roof
6
Dishwasher Mast Landing Middle School Reach In Cooler
High School add cabinets 401 2014-2015 Anticipated Capital Budget
Proposed capital $400,000
Existing capital debt service $383,125
Existing bus payments $166,119
Total capital debt service $949,244
Proposed budget increase $57,381
2015-2016 Anticipated Capital Budget 2015-2016 Anticipated Capital Budget
Buses (2) 77 Passenger (funded through retired bus debt) $0
Audio/Video Enhancements $55,000
Proposed capital $400,000
High School Security System Upgrade $15,000
Morse Street Carpet C Wing
Existing capital debt service $372,175
$20,000
High School Elevator Upgrade $35,000
High School Fire alarm Upgrade $15,000 Existing bus payments $161,423
Mast Landing Resurface Parking Lot $65,000
Pownal Playground Upgrade $10,000 Total capital debt service $933,598
Mast Landing Security Upgrade $15,000
Middle & Mast Landing Outside Lighting upgrade $10,000
Pownal Paving $60,000
Pownal Clock System
Mast Landing Fire protection Upgrade
$10,000
$15,000 Proposed budget decrease -$15,646
Capital Reserves $75,000
Total $400,0007
2016-2017 Anticipated Capital Budget 2016-2017 Anticipated Capital Budget
Bus (1) 77 Passenger (funded through Retired Bus Debt) $0
Vans (2) Replacement $60,000
Pownal Septic System $50,000
Proposed capital $400,000
Middle School Fire Alarm Upgrade $15,000 Existing capital debt service $361,225
Audio/Video Enhancements $55,000
Morse Street Security Alarm Upgrade $15,000 Existing bus payments $147,000
Middle School Security Alarm Upgrade $15,000
Pownal Well & Tanks $45,000 Total capital debt service $908,225
Kitchen Equipment High School Steam Table $16,000
Central Office Roof Main Building $35,000
Morse Street D Wing Carpet $25,000
Proposed budget decrease -$25,373
Morse Street Elevator Upgrade $35,000
Capital Reserves $34,000
Total $400,000
2017-2018 Anticipated Capital Budget 2017-2018 Anticipated Capital Budget
Buses (2) 77 Passenger (funded through retired bus debt $0
Central Office Carpet upper and lower $18,000 Proposed capital $400,000
Morse Street Fire Alarm Upgrade $15,000
High School Roof Replacement $250,000 Existing capital debt service $349,113
Athletic Fields Upgrade $100,000
Capital Reserves $17,000 Existing bus payments $148,200
Total $400,000
Total capital debt service $897,313
Proposed budget decrease -$10,912
2018-2019 Anticipated Capital Budget 2018-2019 Anticipated Capital Budget
Proposed capital $400,000
Bus (2) 77 passenger (funded through retired debt) $0
High School carpet main Hall Classrooms $15,000 Existing capital debt service $281,663
Pownal Fuel Tanks $50,000
Existing bus payments $148,600
Pownal Windows $100,000
High School Tennis Courts $30,000 Total capital debt service $830,263
Athletic Field Lights $100,000
Mast Landing Clocks $10,000
Durham Snow Blower $10,000 Proposed budget decrease -$67,050
High School Bathrooms $40,000
Capital Reserves $45,000
TOTAL $400,0008