FY26 Budget Infrastructure Planning Presentation
Budgets · FY 2025-2026 · 22 pages · 1,159 words · all RSU 5 documents · the district's file →
Superintendent’s Proposed FY 26 Budget - Infrastructure Planning
February 5, 2025
Infrastructure Planning Three Areas Addressed:
● Vehicle & Grounds Equipment Replacement - ○ Plans to update aging fleet within useful life recommendations
● Energy Audit Phases - ○ Phased approach to address capital needs
● Lifesafety Projects - ○ Addresses student & staff safety by further securing buildings, increasing communication, and expanding visibility within and around buildings
Vehicle & Grounds Equipment Replacement
Planning that allows the district to update aging fleet within useful life recommendations for:
● Student Transportation Vehicles ○ Buses & Vans
● Facilities Grounds/Maintenance Vehicles & Equipment ○ Trucks, Van, Tractors, Mowers, Utility Vehicles, various small equipment used to maintenance of grounds and sports fields
Student Transportation Vehicles
Classification Year Number of Buses Average Mileage
Bus 2012 3 149,047
Bus (Handicap) 2015 1 93,474
Bus 2017 2 114,243
Bus 2018 3 108,290
Bus 2019 5 100,108
Bus 2020 1 80,006
Bus 2021 2 46,380
Bus 2022 2 56,004
Bus 2023 1 12,782
Bus 2024 1 2,668
Bus 2026 1 0
Student Transportation Vehicles
Classification Year Number of Vans Average Mileage
Van 2014 2 169,300
Van (Handicap) 2016 1 22,086
Van 2017 2 112,625
Van 2019 1 68,797
Van 2020 4 23,542
Van 2023 1 1,96822 School Buses & 11 Passenger Vans
Buses 10 year life cycle - should be replacing 2 per year Vans 6/7 year life cycle - should be replacing 2 per year
Grounds/Maintenance Vehicles
Classification Year Number of Vehicles Average Mileage
Truck- Dump 2011 1 67,500
Truck 2013 1 102,000
Truck 2016 1 70,900
Van 2020 1 26,0004 Vehicles Truck & Vans 6-7 year life cycle - should be replacing 1 per year
Grounds/Maintenance Equipment
Classification Year Number of Vehicles Average Hours
Utility- Gator 2003 1 2,010
Mower/Tractor 2006-2020 6 395-3,930
Trailers 2005-2023 4 n/a
Tractor 2024 1 n/a
T Attachments 2012 4 n/a
Other Equip 2004-2013 2 245-2,450
Handheld Equip 2024 7 n/aGrounds Equipment Mowers/Tractors 10-20 year life cycle - should be replacing 1 per year
Vehicle & Grounds Equipment Replacement
Recommendation:
○ Use three year term leasing purchasing for three years ○ Year four and beyond - purchase replacement vehicles as part of annual budget ○ Use undesignated fund balance as an offset to incrementally step into consistent annual appropriation ○ Present plan annually for consideration
Vehicle & Grounds Equipment Replacement
2025-2026:
Add $168,000 to annual budget, which will be offset by use of undesignated fund balance
● $465,795 - 3 Yr Lease Purchase ($168,000 per year)
● 2 Buses
● 2 Passenger Vans
● 1 Grounds Truck
● 1 Mower/Tractor
● Miscellaneous Other Field Maintenance Equipment
Energy Audit Phases
Planning that allows the district to address capital needs that were identified during the Energy Audit:
● Phase 1 : ($3,658,926 - 17 Yr Lease Purchase $303,095) ○ Heating Plant Improvements (FHS) ○ Building Automation Upgrades (FHS, FMS) ○ Districtwide Building Automation Integration (FHS, FMS) ○ Miscellaneous Exterior Weatherization (FHS) ○ LED Lighting Upgrades (FHS, FMS, MLS, MSS, PES, DCS, CO) ○ Ceiling Tile Replacements (PES)
Energy Audit Phases
Planning that allows the district to address capital needs that were identified during the Energy Audit:
● Phase 2 : ($2,459,153 - 17 Yr Lease Purchase $203,710) ○ Air Handler Replacements (FHS, FMS, MLS, PES) ○ Terminal Equipment (FHS, FMS, MLS) ○ Mechanical Insulation (FHS, MLS, MSS, PES) ○ Building Automation Upgrades (MLS, MSS, PES, DCS, CO) ○ Districtwide Building Automation Integration (MLS, MSS, PES, DCS, CO) ○ Attic Insulation and Air Sealing (PES) ○ Miscellaneous Exterior Weatherization (FMS, MLS, MSS, PES, CO) ○ Window Improvements (MLS, MSS) ○ Testing and Balancing (FHS, FMS, MLS, MSS, PES, DCS) ○ Duck Air Leak Testing (FHS, FMS, MLS, MSS, PES, DCS) ○ Building Generator (FHS)
Energy Audit Phases
Planning that allows the district to address capital needs that were identified during the Energy Audit:
● Phase 3 : ($2,535,288 - 17 Yr Lease Purchase $210,016)
○ Air Handler Replacements (FHS, MLS) ○ Terminal Equipment (FHS, FMS, MLS) ○ Roofing (MLS, PES) ○ Heat Pumps (CO) ○ ADA Compliant Bathrooms (MSS, PES)
○ Electrical Panel Replacements (MSS, PES)
○ Exterior Restoration (FHS, MLS, MSS) ○ Walk In Cooler/Freezer (FHS, PES) ○ Building Generator (FMS) ○ Exterior Restoration (PES)
○ Asphalt Paving (FMS, MLS, MSS, PES, DCS)
Energy Audit Phases
Planning that allows the district to address capital needs that were identified during the Energy Audit:
● Phase 4 : ($1,540,699 - 17 Yr Lease Purchase $127,627) ○ Domestic Hot Water Upgrades (MLS, MSS, PES, DCS)
○ Air Handler Replacements (FHS, MLS) ○ Walk in Cooler/Freezer (DCS) ○ Building Generator (MSS, PES, DCS)
Energy Audit Phases
Recommendation:
○ Use 17 year term leasing purchasing for phases ○ Use undesignated fund balance as an offset to incrementally step into consistent annual appropriation ○ Present phases annually for consideration
Energy Audit Phases
2025-2026:
○ Approve Phase 1 - enter lease purchase agreement - first payment would be due in 2026-2027 budget year
Life Safety
● Addresses student & staff safety by further securing buildings, increasing communication, and expanding visibility within and around building ○ Single Phase: ($2,434,376)
■ Cameras (FHS, FMS, MLS, MSS, PES, DCS, CO)
■ Door Access (FHS, FMS, MLS, PES, DCS)
■ Phones (FHS, FMS, MLS, MSS, PES, DCS, CO)
■ Paging (FHS, MLS, PES)
■ AED (FHS, FMS, MLS, MSS, PES, DCS, CO)
■ Door Replacements (FHS, FMS, MLS, MSS, PES)
■ Fire Access/Devices (FMS, MLS, PES, DCS)
Life Safety
Recommendation:
○ Use undesignated fund balance to complete projects outside of the local FY26 budget
Life Safety
2025-2026:
○ Make a one time transfer of $2,434,376 from undesignated fund balance to Capital Projects Reserve Account to address Life Safety projects
Funding Proposal for 2025-2026 Budget
● Vehicle & Equipment Replacement $ 168,000 ● Energy Audit Phases $ 0 ● Life Safety Proposal $2,434,376 Total Proposed Use of Undesignated Fund Balance $2,602,376 Estimated Undesignated Fund Balance - Unallocated 1. Un-Audited 2023-2024 General Fund Unassigned Fund Balance $6,710,182 2. Balance used for 2024-2025 Budget Purposes (allocated) ($900,000) 3. Balance transferred to Reserve Account(s) via 2024-2025 Warrant ($1,334,500) 4. Estimated 2024-2025 Addition $1,175,000 5. Estimated Unallocated Ending Balance (1 - 2 - 3 + 4) $5,650,682 6. 5% of 2024-2025 General Fund Operating Budget ($2,075,023) 7. Amount in excess of 5% (5 - 6) $3,575,659
Estimated Unallocated Fund Balance after Recommendations Estimated Unallocated Ending Balance after 2024-2025 Budget Process $ 5,650,682
Balance proposed for 2025-2026 Budget Purposes (allocated) ($900,000) Balance proposed for Tennis Court and Track & Field Reserves ($75,000) Balance proposed for Implementation of Vehicle Replacement Plan ($168,000) Balance proposed for Capital Reserve Account to Implement Life Safety Projects ($2,434,376) Estimated Unallocated Ending Balance after 2025-2026 Budget Process $2,073,306 5% of 2024-2025 General Fund Operating Budget $2,075,023
Mission To inspire and support every learner by challenging minds, building character, sparking creativity, and nurturing passions.
Vision Students graduate as compassionate, honest, and respectful citizens who learn and contribute to their communities for life.
Source: , linked from www.rsu5.org/budget/fy26. Text copied out by software (pdftotext); no wording corrected.